Setting out for white city living project
Completed 2 cores 21 floors each and then started one 27 floors building and completed 4th core of 29 floors
Responsible for setting out, quality assurance, concrete calling and surveys of the cores
Setting out for internal work for Admiralty Arch project
Setting out for brickwork, block work, partition walls, dryliners, small powers, pipe layers, services
Setting out using TS06
quality assurance forms and reports
instructions and report for the subcontractors using site audit pro
Setting out at 23 story slipform
Top down construction
Huge amount of cast in requires attention
Setting out at Riverside 2 project.
I’m looking after 5 building sections and a couple of graduate engineers. I manage precast elements as well slabs, turbine table, sloping decks, long beams for the precast support.
completed the slipform from very start to finish and managed 2 engineers on this section.
Been working with other subcontractors - good interface skills
Managed and monitored site control
Setting out at Hs2 project (Old Oak Common).
Setting out lines and levels for prop beams and capping beams, cranes setting up, high walls, big raft slabs.
Checking rebar.
Used ts16 with ICON software.
Top down construction.
Setting out at Canada Water project.
Setting out for 35 storey main slipform and 3 more smaller slipform all part of the same building.
Setting out for precast stairs.
Traditional slabs setting out.
Setting out at London Bridge project.
13 floors slipform including 2 cores.
Lobby Slabs connecting the 2 cores together.
Precast stairs inside the core.
Traditional slabs up to level 4 and after precast columns.
Rebar inspection and signing off prepour checklists.
As built producing
Continuous setting out and surveying of slipform at Ropemakers Street.
Set up up and set out 25 floors and 19 floors slipform.
Setting out for traditional slabs and tin deck slabs.
As built producing.
Setting out and asbuilts at st James Square.
Paperwork ie RAMS , ITPs , MCRs at Old Street Roundabout
Setting out at 40 Leaderhall street.
Demolition experience.
Setting out for underpinning, breaking and building lines.
Surveying existing steel beams.
Setting out for 12 floors slipform.(12/22-03/23)
Intense setting out including opening, pipes, steel plates, halfens, couplers, kwikerstrip etc.
Jnspecting rebar.
Producing as builts.
Setting out lines and levels.